I-5 northbound will have intermittent lane closures between Exit 59 and Exit 60 from 9 p.m. Wednesday to 5 a.m. Thursday, July 29-30. The left lane will close for about five minutes at a time, and the Exit 59 on-ramp will be closed with a detour to Exit 60.

I-405 southbound will have up to two lanes closed nightly from 11 p.m. to 4 a.m. through Friday, July 31. SR 527's southbound center lane will be closed nightly from 9 p.m. Monday to 12 a.m. Thursday, July 27-30. State Route 203 will have one lane closed nightly on Sunday nights through Friday mornings from July 27 to July 31. State Route 96 will have alternating traffic with flaggers from 7 a.m. to 2 p.m. July 27-31.

πŸ“„ Source: WSDOT β€” Highway Construction & Closures β€” https://wsdot.wa.gov/travel/road-construction
Source receipts16 of 18 claims supported Β· 89%

Legacy automated check: the original source text was not preserved. These earlier verdicts have not passed the current publication checks and may contain errors. Source: original document β†—

  • βœ“
    I-5 northbound will have intermittent lane closures between Exit 59 and Exit 60β€œ005: From 9 p.m., Wednesday, July 29 to 5 a.m., Thursday, July 30: β€’ The left lane of northbound I-5 will close intermittently for about 5 minutes at a time between Exit 59 for SR 506 and Exit 60 for Toledo-Vader Road (mileposts 59 to 60).”
  • βœ“
    The lane closures on I-5 northbound will occur from 9 p.m. Wednesday to 5 a.m. Thursdayβ€œ005: From 9 p.m., Wednesday, July 29 to 5 a.m., Thursday, July 30: β€’ The left lane of northbound I-5 will close intermittently for about 5 minutes at a time between Exit 59 for SR 506 and Exit 60 for Toledo-Vader Road (mileposts 59 to 60).”
  • ⚠
    The lane closures on I-5 northbound are scheduled for July 29-30No usable supporting receipt β€” unverified.
  • βœ“
    The left lane on I-5 northbound will close for about five minutes at a timeβ€œThe left lane of northbound I-5 will close intermittently for about 5 minutes at a time between Exit 59 for SR 506 and Exit 60 for Toledo-Vader Road (mileposts 59 to 60). ”
  • βœ“
    The Exit 59 on-ramp will be closed with a detour to Exit 60β€œThe northbound I-5 on-ramp at Exit 59 will close during construction. A signed detour will direct travelers to use Exit 60.”
  • βœ“
    I-405 southbound will have up to two lanes closed nightlyβ€œ405: Monday, July 27 to the morning of Friday, July 31: Up to two lanes of southbound I-405 between milepost 18.11 and milepost 16.45 will be closed, nightly from 11 p.m. – 4 a.m.”
  • βœ“
    The lane closures on I-405 southbound will occur from 11 p.m. to 4 a.m.β€œ405: Monday, July 27 to the morning of Friday, July 31: Up to two lanes of southbound I-405 between milepost 18.11 and milepost 16.45 will be closed, nightly from 11 p.m. – 4 a.m.”
  • βœ“
    The lane closures on I-405 southbound are scheduled through Fridayβ€œ405: Monday, July 27 to the morning of Friday, July 31: Up to two lanes of southbound I-405 between milepost 18.11 and milepost 16.45 will be closed, nightly from 11 p.m. – 4 a.m.”
  • ⚠
    The lane closures on I-405 southbound are scheduled for July 31No usable supporting receipt β€” unverified.
  • βœ“
    SR 527's southbound center lane will be closed nightlyβ€œ527: The center lane of southbound SR 527 from 214th Street Southeast to the southbound I-405 off-ramp will be closed nightly from 9 p.m. Monday, July 27 to 12 a.m. Thursday, July 30.”
  • βœ“
    The closure of SR 527's southbound center lane will occur from 9 p.m. Monday to 12 a.m. Thursdayβ€œ527: The center lane of southbound SR 527 from 214th Street Southeast to the southbound I-405 off-ramp will be closed nightly from 9 p.m. Monday, July 27 to 12 a.m. Thursday, July 30.”
  • βœ“
    The closure of SR 527's southbound center lane is scheduled for July 27-30β€œ527: The center lane of southbound SR 527 from 214th Street Southeast to the southbound I-405 off-ramp will be closed nightly from 9 p.m. Monday, July 27 to 12 a.m. Thursday, July 30.”
  • βœ“
    State Route 203 will have one lane closed nightlyβ€œ203: From 7 p.m. to 6 a.m. Sunday nights through Friday mornings beginning Monday, July 27, one lane of State Route 203 will be closed for a paving project between just south of Duvall to the Monroe city limits (mileposts 12.53 to 23.20). Flaggers and pilot cars will direct alternating traffic through the remaining open lane.”
  • βœ“
    The closure of State Route 203 will occur on Sunday nights through Friday morningsβ€œFrom 7 p.m. to 6 a.m. Sunday nights through Friday mornings beginning Monday, July 27, one lane of State Route 203 will be closed for a paving project between just south of Duvall to the Monroe city limits (mileposts 12.53 to 23.20). Flaggers and pilot cars will direct alternating traffic through the remaining open lane.”
  • βœ“
    The closure of State Route 203 is scheduled from July 27 to July 31β€œ203: From 7 p.m. to 6 a.m. Sunday nights through Friday mornings beginning Monday, July 27, one lane of State Route 203 will be closed for a paving project between just south of Duvall to the Monroe city limits (mileposts 12.53 to 23.20). Flaggers and pilot cars will direct alternating traffic through the remaining open lane. Effective: Jul 24, 2026, 12:48 PM Expected end: Jul 31, 2026, 6:00 AM”
  • βœ“
    State Route 96 will have alternating traffic with flaggersβ€œ096: Daily from 7 a.m. to 2 p.m. beginning Monday, July 27 to 2 p.m. Friday, July 31, State Route 96 traffic will alternate with flaggers from East Lowell Larimer Road (milepost 4) to State Route 9 (milepost 6) for utilities work.”
  • βœ“
    The alternating traffic with flaggers on State Route 96 will occur from 7 a.m. to 2 p.m.β€œ096: Daily from 7 a.m. to 2 p.m. beginning Monday, July 27 to 2 p.m. Friday, July 31, State Route 96 traffic will alternate with flaggers from East Lowell Larimer Road (milepost 4) to State Route 9 (milepost 6) for utilities work.”
  • βœ“
    The alternating traffic with flaggers on State Route 96 is scheduled for July 27-31β€œ096: Daily from 7 a.m. to 2 p.m. beginning Monday, July 27 to 2 p.m. Friday, July 31, State Route 96 traffic will alternate with flaggers from East Lowell Larimer Road (milepost 4) to State Route 9 (milepost 6) for utilities work.”