← The Vancouver Wire
Infrastructure

SR 9, I-5, I-405 Work Continues in Vancouver

πŸ”Š Listen Β· narrated by Aiden

State Route 9 near Kalloch Road will operate with a single lane and alternating traffic through a bypass road from Aug. 23 to Sept. 14 for fish passage construction.

Interstate 5 will have nightly northbound lane closures from 9 p.m. to 5 a.m. on Aug. 24-26 between mileposts 189 and 191 for maintenance.

Interstate 405 will see rolling slowdowns nightly from 11:59 p.m. to 4 a.m. through Aug. 26, and southbound lane closures on Aug. 24-25 between SR 520 and Northeast 12th Street for pavement repair.

πŸ“„ Source: WSDOT β€” Highway Construction & Closures β€” https://wsdot.wa.gov/travel/road-construction
Source receipts12 of 13 claims supported Β· 92%

Legacy automated check: the original source text was not preserved. These earlier verdicts have not passed the current publication checks and may contain errors. Source: original document β†—

  • βœ“
    State Route 9 near Kalloch Road will operate with a single laneβ€œ009: SR 9 is reduced to a single lane near Kalloch Road (MP 59) with a signal alternating northbound and southbound traffic through a bypass road for 42 days, until Sept. 14 for fish passage construction. Expect delays in the area.”
  • βœ“
    State Route 9 near Kalloch Road will operate with alternating traffic through a bypass roadβ€œ009: SR 9 is reduced to a single lane near Kalloch Road (MP 59) with a signal alternating northbound and southbound traffic through a bypass road for 42 days, until Sept. 14 for fish passage construction. Expect delays in the area.”
  • βœ“
    State Route 9 near Kalloch Road will operate with a single lane and alternating traffic through a bypass road from Aug. 23β€œ009: SR 9 is reduced to a single lane near Kalloch Road (MP 59) with a signal alternating northbound and southbound traffic through a bypass road for 42 days, until Sept. 14 for fish passage construction. Expect delays in the area.”
  • βœ“
    State Route 9 near Kalloch Road will operate with a single lane and alternating traffic through a bypass road until Sept. 14β€œ009: SR 9 is reduced to a single lane near Kalloch Road (MP 59) with a signal alternating northbound and southbound traffic through a bypass road for 42 days, until Sept. 14 for fish passage construction. Expect delays in the area.”
  • βœ“
    State Route 9 near Kalloch Road will operate with a single lane and alternating traffic through a bypass road for fish passage constructionβ€œ009: SR 9 is reduced to a single lane near Kalloch Road (MP 59) with a signal alternating northbound and southbound traffic through a bypass road for 42 days, until Sept. 14 for fish passage construction.”
  • βœ“
    Interstate 5 will have nightly northbound lane closures from 9 p.m. to 5 a.m. on Aug. 24-26β€œ005: Nightly from 9 p.m. to 5 a.m. the next day beginning Monday, Aug. 24 to 5 a.m. Wednesday, Aug. 26, three left lanes of northbound Interstate 5 will close from State Route 526/State Route 527 (milepost 189) to Lowell Road (milepost 191) for maintenance.”
  • ⚠
    Interstate 5 will have nightly northbound lane closures from 9 p.m. to 5 a.m. between mileposts 189 and 191No usable supporting receipt β€” unverified.
  • βœ“
    Interstate 5 will have nightly northbound lane closures from 9 p.m. to 5 a.m. on Aug. 24-26 between mileposts 189 and 191 for maintenanceβ€œ005: Nightly from 9 p.m. to 5 a.m. the next day beginning Monday, Aug. 24 to 5 a.m. Wednesday, Aug. 26, three left lanes of northbound Interstate 5 will close from State Route 526/State Route 527 (milepost 189) to Lowell Road (milepost 191) for maintenance.”
  • βœ“
    Interstate 405 will see rolling slowdowns nightly from 11:59 p.m. to 4 a.m. through Aug. 26β€œ405: Nightly from 11:59 p.m. to 4 a.m. the next day beginning Monday, Aug. 24 to 4 a.m. Wednesday, Aug. 26, expect intermittent rolling slowdowns on both directions of Interstate 405 from Northeast 145th Street (milepost 21) to Coal Creek Parkway/Newport Way (milepost 10) for PSE utilities work.”
  • βœ“
    Interstate 405 will see rolling slowdowns nightly from 11:59 p.m. to 4 a.m.β€œ405: Nightly from 11:59 p.m. to 4 a.m. the next day beginning Monday, Aug. 24 to 4 a.m. Wednesday, Aug. 26, expect intermittent rolling slowdowns on both directions of Interstate 405 from Northeast 145th Street (milepost 21) to Coal Creek Parkway/Newport Way (milepost 10) for PSE utilities work.”
  • βœ“
    Interstate 405 will see rolling slowdowns nightly from 11:59 p.m. to 4 a.m. through Aug. 26 for pavement repairβ€œ405: Nightly from 11:59 p.m. to 4 a.m. the next day beginning Monday, Aug. 24 to 4 a.m. Wednesday, Aug. 26, expect intermittent rolling slowdowns on both directions of Interstate 405 from Northeast 145th Street (milepost 21) to Coal Creek Parkway/Newport Way (milepost 10) for PSE utilities work.”
  • βœ“
    Interstate 405 will see southbound lane closures on Aug. 24-25 between SR 520 and Northeast 12th Streetβ€œ405: From 9 p.m. Monday, Aug. 24, to 5 a.m. Tuesday, Aug. 25, two lanes of southbound I-405 will close between SR 520 and Northeast 12th Street for crack sealing and pavement repair.”
  • βœ“
    Interstate 405 will see southbound lane closures on Aug. 24-25 between SR 520 and Northeast 12th Street for pavement repairβ€œ405: From 9 p.m. Monday, Aug. 24, to 5 a.m. Tuesday, Aug. 25, two lanes of southbound I-405 will close between SR 520 and Northeast 12th Street for crack sealing and pavement repair.”

The Vancouver Wire is free. Get Vancouver's news delivered every morning.